Battling the elements to deliver on our promise – a modular data centre in four months

HomeBlogsBattling the elements to deliver on our promise – a modular data centre in four months

We handed over ownership of the modular data centre to Verne Global on Friday 24th November – well within our four-month delivery timescale. We’re very proud of this achievement as we had a number of weather related issues to overcome along the way to make sure the data centre was ready in time for the first customers to move in…

Recent posts

Why your organisation needs to migrate to Microsoft Teams

From November 2019 to May 2020, the number of daily Microsoft Teams users has increased from 20 million ...
Continue Reading

5 ways multi-cloud is accelerating cloud migration

48% of leading IT decision-makers intend to begin a cloud migration project in the next six months. Cloud ...
Continue Reading

A guide to migrating from Skype For Business to Microsoft Teams

How to plan your migration to Intelligent Communications Microsoft Teams has the potential to significantly improve productivity, but ...
Continue Reading